Old Court project

Key updates -
26/02/2026

Phase 2: Countdown to completion - almost nearly there!

  • Most of the hoarding outside G Arch, next to the Scholars' Garden has been removed. It and the temporary Heras fencing will disappear with the last of the scaffolding.
  • The remaining building compound and equipment on Front Court is due to be cleared by 6th March. This includes the removal of the temporary cycle racks which will cease to be available from 2nd March.
  • Turfing in Old Court will take place between 2nd - 4th March. There will be heavy machinery in use and turf delivered on pallets via The Avenue so please take care.
  • Turfing in Front Court and the Scholars' Garden will follow during 10th - 13th March.
  • Final scaffolding removal from the Scholars' Garden and G Arch is targeted for imminent completion with Saturday working this weekend.
  • All refurbished rooms have been returned to the College with just the cleaning of some floorboards remaining to complete the redecoration of E Stair.
  • From 12th March, following removal of all scaffolding, the lightening conduction can be fully connected within Old Court and on the King's College elevation. This will involve a mobile work platform.
  • Over the Easter break minor works to the Phase 1b guttering will be completed using a mobile work platform.
  • The external doors to the stairs of A, D, E and F will be refurbished as part of the Phase 2 scheme in June when weather conditions are favourable.
  • Competition update: the total number of slates used during Phase 2 as assessed by the Collyweston slate supplier was 52,500 of which 15,000 were recycled from the original roofing. Thank you to the 60 entrants who took part. The closest answer was 50,000 and the student winner will be notified shortly. The range of estimates was 590 - 321,000!

Recap

Phase 1a was completed in October 2020 after 2 years’ work, and comprised re-roofing of the North Range as well as modernisation of the Porters’ Lodge, refurbishment of facilities in the basements of E and G staircases and student rooms in A and B staircases, a new fire escape, the rewiring of C staircase and the construction of a new plant room.

Phase 1b saw the construction of the River Room café; new steps with a concealed lift to the North Range to allow full accessibility to all the main spaces of Old Court (for the first time in the College’s history); the refitting of the main College kitchens; and the construction of a new three-storey extension in the North Passage incorporating a new servery area, toilet and accessible facilities, a lift and fire escape.

Is this website helpful?

If you have any further questions please email OldCourtPhase2@clare.cam.ac.uk